  • Crews will continue laying forms and pouring concrete for sidewalks and driveways between Friday, October 28 and Friday, November 4, as weather permits.
  • People who live along the west side of Home Avenue in the work area will not be able to access their driveway for about 6 days while form boards are placed and the concrete cures.
  • Crews will wait for dry enough weather to continue laying forms and pouring concrete for sidewalks and driveways for the remaining areas: between Park Street and Ada Lane and a few areas north of Jackson Street.
  • They may work additional days and times with pre-approval from the City. Monday through Friday (although the typical workday ends before 5 p.m.).
  • The city will issue a project corrections list the week of November 21, after which Kerr will begin doing minor repairs.Ĭrews may work from 7 a.m.
  • Fill in areas in front of and behind the sidewalk.
  • Repair curbs and other items in select locations.
  • Build the stormwater facilities (swales).
  • Build the rock-lined ditch at the south end of Wood Avenue near Railroad Avenue.
  • #Last wood official website install

    Asphalt paving in the parking lot at the Home Ave Apartments, install a few more asphalt driveways, and add asphalt at a couple smaller locations around drains on Home Avenue.Build and plant the stormwater facilities (swales).Place topsoil and bark mulch, where needed, behind the new sidewalk.Place gravel along the shoulder of the road.If you will be affected, you will receive a door notice in advance. Some Home Avenue residents will experience approximately one-hour water shut offs while crews raise the water meters. Install water meter boxes and mailboxes.Kerr’s crews will be working on this list over the next couple of weeks. A “Project Corrections List” will be issued to the contractor this involves numerous items on both Home and Wood that need to be repaired or corrected.Place plantings in the stormwater facilities (swales).Place topsoil and bark mulch, where needed, in front of and behind the new sidewalk.Place topsoil and seed mix, where needed, beyond the gravel shoulders.

    last wood official website

    Some Home Avenue residents will experience approximately one-hour water shuts while crews raise the water meters. However, schedules may fluctuate due to weather, conditions underground, subcontractor schedules, or materials availability. Our contractor Kerr does their best to stay on schedule. Thank you very much for your patience over the past seven months, Tracie

    last wood official website

    We hope that you are enjoying the new sidewalk and new pavement! I’ll send a message in the coming days about maintenance responsibilities with taking care of the new sidewalks and landscaped areas. Near the end of this period, city staff will check on the construction work and new landscaping and determine if additional repair or maintenance work is needed. The project will then begin a two-year period in which Kerr is responsible for problems with materials and workmanship. Soon this improvements project will transfer back to city ownership, and our contractor Kerr will leave the area.